June Construction Update
June Construction Update
2 min read
Richard Crookes Construction are making good progress with concrete slabs, now poured to level 10. From here a new level is due to be poured every 18 days. The jump form (the central formwork systems designed to construct lift and stair cores in high rise buildings) is now up to level 14.